Note that page is still in development. The preliminary sharing of this information is intended to benefit the ETOR initial implementers in preparation for their implementations, with the understanding that some information may change as our development evolves.
In collaboration with CDC, APHL has technical assistance subject matter experts whose mission is to assist public health partners in implementing data exchange solutions. The ETOR Detor team will provide expertise in project management, laboratory workflow, terminology support, technical architecture and systems integration.
...
Prepares your team for long-term sustainability.
Approach By Phase
...
Table of Contents | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|
|
Pre-Implementation
The pre-implementation phase will be focused on strategizing and preparing for the ETOR Detor project, particularly in the areas of legal execution, staff allocation, and completion of a public health laboratory and healthcare organization profile.
...
The planning and analysis phase will be focused on gathering data on the operational and technical processes of both the public health laboratory and the healthcare organization(s). This data will be analyzed to prepare for the intermediary Detor configuration and support the organization in the design of the new operational and technical processes that will exist with ETORDetor.
The primary components of this phase include:
- Project Kick-Off
- Commitment to Project Schedule
- Commitment to Project Charter
- Initial Use of Project Control Measures (Communication, Issue/Risk/Change Managment, and Status Reporting)
- Analysis, design and approval of test order and results workflows for selected test types
- Analysis of data for selected test types (gap analysis)
- Analysis of current technical environment
- Integration/Connectivity planning
- Provide healthcare organization test order message (via email)
- Provide public health laboratory test result message (via email)
- Collection of pre-ETOR Detor evaluation metrics
Configuration
The configuration phase will establish the required transport and routing, message transformation and translation, terminology services, and monitoring for the unique public health laboratory and healthcare organization(s).
...
- Mapping/Translation of healthcare data elements to the intermediary Detor data elements
- Mapping/Translation of the public health laboratory data elements to the intermediary Detor data elements
- Establishing connectivity
- Creation of the intermediary test order and results messages
- Configuration of monitoring tools
...
The validation phase will include the coordinated testing of the ETOR Detor operational and technical processes. This phase will be supported by APHL but will require focus and coordination between APHL, the public health laboratory, and the healthcare organization.
...
- Validation of connectivity and data flow
- Validation of successful test ordering for all scenarios associated with select test types
- Validation of successful test resulting for all scenarios associated with select test types
- Validation of expected error handling
- Validation of monitoring tools
- Validation of operational processes
- Updates to intermediary Detor configuration as needed
- Training of staff in ongoing ETOR Detor support and maintenance responsibilities
- Approval for public health laboratory to proceed to production
- Approval for healthcare organization(s) to proceed to production
...
The production phase will include the “go-live” of ETOR Detor and 1-2 weeks of on-site post-production implementation team support.
The primary components of this phase include:
- ETOR Detor Productive Use
- Validation of productive operational and technical processes
- Transition to AIMS Support team
- Collection of post-implementation evaluation metrics (this may occur several months following productive use)