AIMS>DEX Most dev is done, terraform updates in progress--targeted for end of April
Outstanding items:
Support documentation and Training
Will need production credentials for sending to DEX
Aims may not be ready by end of month for training --late May be target in order to complete training
Can still send to STG
1 file AIMS sent, aims received success message, but DEX did not actually receive file, attempted to re-play, got another success message, but was not received; re-initiated with entirely new id…
Only 1 file identified, on AIMS side cannot determine if file is persisted on DEX side <<this is biggest blocker on AIMS side
Was identified through manual cross-checks, not sustainable long-term
Need to potentially brainstorm solution
Cosmin:
Onboarding to SAMS prod--can send invitation--1-2 days
Not sure about the ongoing issue--Anthony is investigating, reviewing logs to determine what happened
Geo: Root cause is unknown, open to developing solution to automatically detect and replay, building some way to doublecheck that everything was indeed uploaded outside if TUS protocol
CDC: Have not planned to build new development to send ACK outside TUS protocol
Dex ready to go live by end of April, AIMS would be ready to go live by May
Erroll: Currently doing UAT with CELR--Targeted completion by 4/15, 1 issue identified
Few portal deployments updates, displaying data
Going through reconciliation tests and parallel test--identified discrepancy of about 22 million records out of 5 billion (discrepancy in processing data after data is received to HHS protect and DCIPHER--SO HISTORIC DATA)--trying to determine delta, and will be discussing with programs as to how to handle
Going through security checks, and through ORR
As of right now, still a go, but some risks, could be ready by end of month
kind of yellow, dependent on discrepancy and security
Is not asking APHL to send historic data
Target deadline: Concern about May prod date? Erroll: CELR contract ends at end of April so will need to discuss with programs
Current feed to CELR on AIMS would be maintained, potentially 1-2 weeks of parallel processing to DEX Production, then would turn off CELR feed on AIMS
Would need to go through same decommissioning process for CELR
DEX: Will plan to go into production by end of April 2024 (will need to address ACK/missing file)
Geo: Currently credentials are tied specifically to SAMs, but are there system credentials which could be provided?
Cosmin: Would onboard additional developers with additional credentials; SAMs may be deploying admin/machine credentials next year
Geo: will request additional credentials for additional developers-- Geoffery Miller will identify list of developers and will send to Anthony
Dex Meta Data Version 2: GM: Plan to have DEX meta Version 2 by time we go to prod in May, will send test messages to test and STG environments
Anthony: Will discuss next week, few new fields/mapping
Checkpoint- Anthony to schedule meeting for Thursdays at 11am ET
Action items
Quick decisions not requiring context or tracking
For quick, smaller decisions that do not require extra context or formal tracking, use the “Add a decision…” function here.
Decisions requiring context or tracking
For decisions that require more context (e.g., documentation of discussion, options considered) and/or tracking, use the decision template to capture more information.