| Dev Updates: Production Readiness Review and Migration Steps ER: Parallel processing to CELR and DEX/CDC; Existing pipeline will continue to be maintained (CELR on AIMS will continue to be supported) General timeline for high-level timeline--there is a upload release on the DEX side which will need to implemented which will take ~1 day REVISION 3TIMELINE - 5/15 - v2 CELR Routing updates to staging - 5/15 - CELR ready for v2 in staging - 5/22 - APHL deploys /info endpoint check and v2 to staging - 5/22 - 5/28 - APHL | DEX | CELR End to End verification in staging - 5/28 - DEX outage comms - w/o - v2.0.X CR Approval - 5/28 - APHL change control request - 5/28 - v2 CELR Routing updates to production - 5/28 - CELR ready for v2 in production - 5/30 - proposed Upload v2.0.x production release - 5/31 - GO/NO GO DECISION - 6/3 - pre-cutover meeting - 6/3 - APHL proposed cutover - Production monitoring - APHL | DEX
Checkpoints during the production migration
|