Date

Attendees:

APHL

CDC

Peraton

Dari Shirazi:

Megan Light: --

Erroll Rosser:

Vanessa Holley : --

Teresa Jue: --

Kristin Peterson :

Gretl Glick:

Cheri Gatland-Lightener: --

Tom Russell:

Geo Miller:

Norris Kpamegan :

Marcelo Caldas:

Alissa McShane:

Ryan Harrison:

Don Lindsay:

John Reaves:

Marion Anandappa:

Scott Rank

Rohit Panwar: X

Leslyn Mcnabb: X

Goals

  • Update on Data Lake Migration Status

  • DEX Overview and Status Update

  • Go/No-Go Decision for load testing CELR>DEX Sep 12-14

Discussion topics

Item

Notes

Overall Status Updates

  • AIMS connection to DEX options: Research/Analysis: In Progress

    • AIMS/APHL Updates:

      1. Development tasks completed, resources identified: Ready for load testing Sep 12-14

        1. Updates/blockers:

      2. DEX: Complete internal load testing:

        1. Update:

        2. AIMS: Send CELR Production data (n = 24 hours~) to DEX STG Environment: Target: ~August 21, 2023 (will confirm dates as we assess readiness)

          1. Load testing sending CELR Prod data to DEX STG: would include HL7 and CSV

          2. Criteria/Parameters for ingestion component testing:

            1. Volume: 10-20 terabytes per month; ~50 gig/day

            2. Period of Reporting: DEX: Preference is to receive 3 days of data [completed days--sequence-- low, average, high volume]

            3. Data Type: HL7 and CSV

          3. Dex Update:

            1. Readiness:

Mtg Notes:

  • Notes:

Consensus Decision

Decision:

Questions

  • Go/No-go meeting: 9/7: 12-1pmET @gretl will send updated meeting invite

Next Steps & Action Items

Next steps:

Previous Action items

  • Completed: Geoffery Miller dari.shirazi@aphl.org AIMS: Confirm & identify ongoing operations, resources, support/training for AIMS>DEX, Upload API: Tentative: Late August

  • In progress: DEX: Continue internal DEX performance/load testing: Target Readiness: August 31, 2023

  • Not yet started: AIMS: Send CELR Production data (n = 24 hours~) to DEX STG Environment: Target: ~Sep 12-14, 2023