12/20/23 CA TB LWP Weekly Meeting Notes

Date

Dec 20, 2023

Attendees

APHL

CDC

CDPH

APHL

CDC

CDPH

Anne Gaynor
Angela Starks
Zenda Berrada
Sarah Buss
Lauren Cowan
Varvara Kozyreva

 

 

 

 

 

 

 

 

Goals

  • Review status updates for new development, open issues, enhancement requests for the TB LWP Project

  • Review Project Schedule

  • Identify Next Steps and action items

Discussion topics: APHL/CDC TB Weekly Checkpoint

Item

Notes

Item

Notes

OOOs

  • Steven OOO:

    • Dec 11, 22-25

  • Gretl OOO: 12/19 ( am) 12/22-1/2

  • Varvara: 12/20- conflict

  • Katelyn- 12/19-20

  • Shawnte: 12/22

  • Allison: 12/19-1/2

  • APHL Offices: Closed the last week of December (12/25-29, Jan 1)

  • ICC Offices closes ( Dec 25- Jan 2)

TB LWP: Issue Log

Published Link: https://app.smartsheet.com/b/publish?EQBCT=1136271a8d2e4fa184ebc0833df46742

Smartsheet: https://app.smartsheet.com/sheets/8q4pGFcfXc4mmgCw5Q4CQ43j93G6ChHCjxQ5pGm1

  1. Issue 161: Confirm process for tNGS if ordered in LWP prior to being completed in CDPH StarLims Production Ready for Retest

    1. 12/6 Options were discussed the consensus would be to use option 1 workflow. Option 1: TNGS is "ordered" prior to it being ready in CDPH SL, lab manually switches to PSQ. This would reduce the impact of having to retest, they could make changes in batch mode.

    2. 12/13: CDPH SL manual process to be tested.

    3. 12/20: Steve to test the manual switch and provide an update.

  2. Issue 162: MTB Sediment, unable to enter positive Open

    1. 12/20: New sample was submitted and there were no further issues as now. Closing issued

  3. Issue 164: Preapproval Message TRF ready for retest

    1. 12/20: Will notify Varvara to retest

  4. Issue 165: Incorrect mapping of comments and culture type open

    1. 12/20: Comments were made in Smartsheet that the fields can not be split. Steven will reache out to LIMS and verified that they are indeed the same stored field in LIMS. Follow up with Katelyn and Varvara

  5. Issue 167: Micro Results- DST Drug resolved

  6. Issue 168: TRF Update; Submitter Requested test

    1. 12/20: update that the field has been correct Ready for retest

  7. Issue 169: Specimen Source update resolved

TB Testing Updates Target Deadlines

  • CDPH: Validation schedule for expected TB Testing:

    • tNGS should be available for ordering in StarLims Production by Jan 1, 2024

      • 11/22/23: Validation in progress (placeholders in place?): Current Target: Jan 31, 2024

    • WGS: should be available for ordering in StarLims Production by October 1, 2023

      • 12/7/23: Moved to StarLims Production Complete

    • PSQ: Will no longer be available for ordering as of December 31, 2023

      • 12/6: Verified that the PSQ would return, working similar to a reflex test.

    • WGS go-live--roll out to submitters/ready for ordering:

      • Webinar for submitters: Jan 2024

      • Ideal path forward: Go-Live when validation is complete, in SL production, and LWP is ready for production deployment

      • 12/6: Final package is under review with the Lab Director.

      • 12/20 Approved; Share with CDC , Sync with Vavara

      • RISK: TB Testing SHUTS DOWN if PSQ runs out--which may happen in January. Enough reagent to March

  • Project Schedule: https://app.smartsheet.com/b/publish?EQBCT=ea47c05f36e245439ca44e53c66696a1

    • Targeted Testing complete 12/22/23

      • 12/20: Need an update from Katelyn on progress with testing and if we are still on track.

    • SB deployment 1/10/24

    • Production 1/16/24

      • 12/20: Discussion on if we had to push out, the latest we would like to propose is 1/23

TB LWP: WGS & tNGS TRF Updates

Outstanding Questions

 

 

Next Steps & Action Items

  • TB webinar for submitters, need to set a date for training.

    • 12/20: TBD, planning. Target one week out from set go-live date. 1/9 preliminary communication with submitters.

  • User guide updates: Ann to send most recent Word version , to begin working on updates

    • 12/20: Gretl to review and provide updates. Coordinate timing of release, goal is to have ready to present at webinar and switch to new version

  • Website: Varvara to work on documents that will drive website changes

    • 12/20: Varvara working on documents ( workflows, etc) to send

 

 

Action items

Item

Responsible Party

Due Date

Item

Responsible Party

Due Date

Round trip testing

Kathelyn/Steve

December 22, 2023

Feedback on follow up for issues 164, 165 and 168

Katelyn/Vavara

December 21,2023

User Guide Updates

Ann/ APHL

TBD- before Production Deployment

Website update

Varvara/APHL

TBD- before Production Deployment

Historic Archive of Meeting Notes:

https://app.smartsheet.com/sheets/fcQf4RmFmQ3jRcf4mJ2JMjw4vFmpgPCW63vp4Qh1

CA TB LWP Issue Log & Enhancement Requests:

https://app.smartsheet.com/sheets/8q4pGFcfXc4mmgCw5Q4CQ43j93G6ChHCjxQ5pGm1